Provider Reference Infrastructure Sharing Offer
______________________________________________________________________
[Infrastructure Provider may replace this SLA by his own version(s), subject to approval
by the Authority]
1. Introduction
This Annex details the service levels to which Provider commits with regard to the
provision and repair of Services covered by this Agreement. Services are at all
times provided subject to the terms and conditions as set out in this Agreement.
The Services described in the SLA are subject to the Technical Manual and Operations
& Maintenance Manuals which define the detailed operational processes associated
with the provision of the Services.
2. Service Provisioning
If Provider does not meet or does not expect to meet any planned delivery timescales
specified as a milestone within this schedule, the Operations & Maintenance Manual or
an associated delivery plan, Provider shall confirm to the Infrastructure Seeker as soon
as the delay has been identified. Provider will include the reasons for the delay and the
expected duration of the delay.
Provider will endeavour to keep the delay as short as possible. Both Parties shall agree
upon a new date for the delayed milestone. Consequently, any previously agreed Ready
for Service Date will be cancelled and replaced by a new Ready for Service Date, the
new Ready for Service Date being automatically derived using the normal milestone
schedule as per the Operations & Maintenance Manual, unless there is a material
reason why Provider may need to further delay the Ready for Service (RFS) date. For
the avoidance of doubt, for the purpose of the calculation of penalties, the original Ready
for Service Date shall apply, unless otherwise agreed by the Parties.
The following table defines the penalties to be applied, in case Provider is the cause for
delay of RFS date:
Delay of RFS date
(due to Provider delays):
Compensation for each working day of
delay
For the first 10 working days
(until 10th working day)
For the following 10 working days
(until 20th working day)
For each working day after the 20th
working day.
0.5% on one-time installation fee
1.25% on one-time installation fee
2% on one-time installation fee
Maximum compensation to be applied (in
total): 50% on the upfront fee)
3. Repair
3.1.
DATE
Repair Provision applicable to all Services
Page 2
Sélectionner le paragraphe cible3