976
(4) Failure to respond to official correspondence or request for additional information may be the cause for
rejection which rejection:
(a)
shall be without prejudice where an application has not yet been considered; or
(b)
may be made with prejudice after an application has been fully reviewed by the Authority
Notice of violations
79. (1) Subject to subrule (2), the licensee shall, within 15 days from receipt of a notice of violation or such
other period as may be specified in such a notice, submit a written response to the Authority
(2) If the response contemplated in subrule (1) cannot be sent within the period contemplated in subrule
(1) or such specified period: by reason of illness or other unavoidable circumstances, acknowledgement of
the notice of violation, together with a request for an extension of time setting forth a satisfactory
explanation of the delay and the reasons for the extension shall be flied with the Authority
(3) Subject to subrule (4) the response to each notice of violation shall:
(a)
be in duplicate and properly completed; and
(b)
not be abbreviated by reference to other communications or responses toother notices
(4) lf the notice of violation relates to:
(a)
violations that may be due to the physical or electrical characteristics of transmitting
apparatus: the response shall indicate what corrective steps, if any, have been taken to
prevent future violations, and, if any new apparatus is to be installed the�� date such
apparatus was ordered the name of the manufacturer and the promised date of delivery;
(b)
lack of attention to or improper operation of the transmitter, the name and licence number
of the operator in charge shall be given
(5) If the installation of the apparatus contemplated in subrule (4)(a), requires an additional licence, the file
number of the application shall be given, or if a file number has not been assigned by the Authority such
identification as will permit identification of the application
Content of station records
(1) Licensees of each station shall maintain station operation records, which shall include the following
information
(1)
dates and hours of operation;
(2)
all measurements of the frequencies), including the name of the person making the
measurements, the exact frequency measured or the observed deviations from the
assigned frequencies) expressed in Hertz kilohertz or percent plus or minus and a
statement of any corrective action taken
(3)
emitted power
(4)
types of emission;
(5)
chronological record of experimentation conducted; and
(6)
the name of the operator on duty