1008  CHAPTER XI ­ GENERAL  PART  20  Entry Upon Land  Access and use of public property  147.  (1)  When  a  telecommunications  services  provider  or  operator  intends  to  constructor  install  any  telecommunications  facility on  public property,  a  copy of   the  request  for approval  submitted  under section  55(2) of   the  Act to  the  administrative  authority having jurisdiction  over the  property shall  also  be  submitted  to the Authority.  (2) The submission referred to in sub­rule (1) shall be accompanied by a certificate signed by a responsible  officer of the provider or operator:  (a)  that  all  permits  and  approvals  required  by  other  Government  agencies,  including  such  permits  or  approvals  as  may  be  required  by  environmental  law  have  been  applied  for;  and  (b)  a statement identifying the­  (i)  nature and purpose of  the proposed telecommunications facility;  (ii)  any existing telecommunications and/or radio licence pursuant to which permission  to operate the proposed facility has previously been granted by the Authority;  (iii)  the technical specifications of the proposed facility;  (iv)  the  extent  of   any  facilities  sharing,  co­location  or  other  agreements  pertaining  to  the proposed telecommunications facility;  (v)  the extent of the construction required; and  (vi)  the length of the construction period.  (3)  If   a  current  and  valid  telecommunications  or  radio  licence  covering  the  telecommunications  facility  proposed  to  be  constructed  on  public  property  has  not  been  issued  by  the  Authority,  the  documents  required  by  sub­rules  (1)  and  (2)  may  be  submitted  as  attachments  to  an  application  for  a  new  telecommunications or radio licence.  (4)  Telecommunications  and  radio  licenses  for  telecommunications  facilities  that  require  the  approval  of  other Government agencies shall be issued  on a provisional basis subject to the condition that the applicant  obtain all other necessary approvals.  (5)  Provisional  licences  shall  become  final  upon  the  satisfaction  of  the  conditions  stated  therein,  and  to  permits  and  approvals  from  other government  bodies,  evidence  theta  condition  has  been  satisfied  shall  be  submitted  to  the  Authority  in  the  form  of  a  copy of  the  approval  issued  by the  relevant  government  body or  bodies  identified  in  the  condition  and  upon  the  submission  of  the  approval  referred  to  in  this  subsection!  a  provisional  licence  is  deemed  to  have  become  final  7  days  following  the  submission  unless  the  Authority  takes further action.

Select target paragraph3

Connect to a paragraph
Connect to an entity
Disable highlights
Add to table of contents