- 20 -
In the event that works require final expropriation, the ownership laws in force
shall be applied if no conciliatory settlement has been reached between the
Ministry and the proprietor.
Article 50
The Ministry may ask tree owners to cut branches extending over phone lines if
the branches cause, or are likely to cause damage, to the lines. If the tree owner
does not cut the branches, the Ministry shall cut them at his expense.
Article 51
If the Ministry’s projects require the installation of a phone line on a public
road whose sides have already been occupied by electricity lines, the owners of
such lines shall remove them or reinstall them in such a technical way as to
accommodate the Ministry’s project.
Article 52
If any competent authority intends to install electricity lines beside or across
phone line networks, it shall take, in agreement with the Ministry, the
preventive measures necessary to secure the phone lines from the impact of
electrical frequencies.
Article 53
If any competent authority or local council intends to carry out constructions,
digging, filling up or repair works on the public main road or sub-road beside or
across phone line networks, they shall obtain a permit, in advance, from the
Ministry of Telecommunications.
Article 54
Select target paragraph3